Vantosh bv (vantosh)
Status Tracking
Payment not yet submitted
NGI.POINTER.Gigabit.ASIC
- Bug #861:
PowerEL ppc64sffs building hardware
- €5000 which is the total amount
- this task is part of MoU Milestone Bug #850
MoU Milestone subtotals for not yet submitted payments
- Bug #850:
NGI POINTER Milestone 3
- subtotal €5000 out of total including subtasks of €57000
NLnet.2022-08-107.ongoing
- Bug #852:
implement grevlut*
- €500 out of total of €2000
- this task is part of MoU Milestone Bug #1027
- Bug #1004:
FPGA bring up for platform definitions
- €300 out of total of €1500
- this task is part of MoU Milestone Bug #1037
- Bug #1024:
Second phase of nmigen Dynamic Partitioned SIMD and nmigen language improvements
- €1000 out of total of €6000
- this task is a MoU Milestone
- Bug #1026:
implement Draft Instructions in nmigen HDL
- €500 out of total of €5000
- this task is a MoU Milestone
- Bug #1031:
implement CRweird instructions in ISACaller
- €1500 out of total of €3000
- this task is part of MoU Milestone Bug #1027
- Bug #1032:
Implementation of SVP64 features: elwidth overrides and REMAP
- €3000 out of total of €8000
- this task is a MoU Milestone
- Bug #1034:
implement crternlogi crbinlut and binlut in ISACaller
- €1500 out of total of €3000
- this task is part of MoU Milestone Bug #1027
- Bug #1047:
SVP64 LD/ST Data-Dependent Fail-First providing linked-list walking
- €1000 out of total of €3000
- this task is part of MoU Milestone Bug #1027
- Bug #1128:
Find a way to check that the SFFS binaries have no VSX instructions.
- €300 out of total of €2500
- this task is part of MoU Milestone Bug #999
- Bug #1132:
Build qemu without **GUEST** vsx (***GUEST*** is SFFS only)
- €300 out of total of €2500
- this task is part of MoU Milestone Bug #999
MoU Milestone subtotals for not yet submitted payments
- Bug #1027:
implement "necessary" additions to SVP64 and Scalar Power ISA
- subtotal €4500 out of total including subtasks of €24000
MoU Milestone subtotals for not yet submitted payments
- Bug #1037:
improvements of Libre-SOC core support on FPGA boards
- subtotal €300 out of total including subtasks of €6000
MoU Milestone subtotals for not yet submitted payments
- Bug #1024:
Second phase of nmigen Dynamic Partitioned SIMD and nmigen language improvements
- subtotal €1000 out of total including subtasks of €6000
MoU Milestone subtotals for not yet submitted payments
- Bug #1026:
implement Draft Instructions in nmigen HDL
- subtotal €500 out of total including subtasks of €8000
MoU Milestone subtotals for not yet submitted payments
- Bug #1032:
Implementation of SVP64 features: elwidth overrides and REMAP
- subtotal €3000 out of total including subtasks of €8000
MoU Milestone subtotals for not yet submitted payments
- Bug #999:
SFFS Operating System Porting
- subtotal €600 out of total including subtasks of €10000
NGI.SEARCH
- Bug #1106:
Experimental SVP64 string/memory routines
- €50000 which is the total amount
- this task is part of MoU Milestone Bug #1102
- Bug #1109:
Integrate optimised SVP64 routines in libc6
- €30000 which is the total amount
- this task is part of MoU Milestone Bug #1103
MoU Milestone subtotals for not yet submitted payments
- Bug #1102:
NGI Search Milestone 2 - MVP Development
- subtotal €50000 out of total including subtasks of €75000
MoU Milestone subtotals for not yet submitted payments
- Bug #1103:
NGI Search Milestone 3 - Technology Adoption Plan
- subtotal €30000 out of total including subtasks of €45000
Submitted to NLNet but not yet paid
NGI.SEARCH
- Bug #1101:
NGI Search Milestone 1 - Kick off Meeeting and IMP
- submitted on 2023-05-26
- €22500 out of total of €30000
- this task is a MoU Milestone
MoU Milestone subtotals for submitted but not yet paid payments
- Bug #1101:
NGI Search Milestone 1 - Kick off Meeeting and IMP
- subtotal €22500 out of total including subtasks of €30000
Paid by NLNet
NGI.POINTER.Gigabit.ASIC
- Bug #860:
PowerEL ppc64sffs
- paid on 2022-12-16
- €25000 out of total of €40000
- this task is part of MoU Milestone Bug #912
MoU Milestone subtotals for paid payments
- Bug #912:
NGI POINTER Milestone 4
- subtotal €25000 out of total including subtasks of €73000